Please enter keywords to search

Global |EN

Choose your country & Language

Asia Pacific

Australia & New Zealand
India
Indonesia
Korea
Malaysia
Singapore (Sunlight)
Vietnam

West Asia and Africa

CHINT-EGEMAC
South Africa
UAE

Europe

Italy
Spain
Turkey

North America

Mexico

Latin America

Brazil
Peru

Choose your country & Language

Australia & New Zealand
India
Indonesia
Korea
Malaysia
Singapore (Sunlight)
Vietnam
CHINT-EGEMAC
South Africa
UAE
Italy
Spain
Turkey
Mexico
Brazil
Peru

Please enter keywords to search

Your search term contains restricted words. Please use different keywords.

CHINT Accelerated to Protecting the Heart of Mexican Wind Farm

MARCH 13, 2023

the-Heart-of-Mexican-Wind-Farm-20230313
the-Heart-of-Mexican-Wind-Farm-20230313
the Heart of Mexican Wind Farm 20230313

Recently, there was news from CHINT Mexico: The 400kV replacement transformer supplied by CHINT to the Reynosa Wind Farm has been successfully running since it was installed and commissioned in November 2022. 

The Reynosa Wind Farm is one of the largest wind power projects in Mexico and Latin America, developed and constructed by Zuma Energia. It is located near the city of Reynosa in the state of Tamaulipas, Mexico, and has a total installed capacity of 424MW with 123 wind turbines and annual average utilization hours of over 4100 hours.

At the beginning of 2022, two 400kV transformers at the Reynosa Wind Farm malfunctioned, leading to a complete halt of the wind farm’s power generation. Besides facing significant losses due to the power outage each day, there was also a constant risk of widespread power outages.

CHINT was invited to conduct a survey and provide a solution to the problem. As we all know, the main transformer is the “heart” of the substation and is crucial for the safe and stable operation of the power grid. Its reliability is of utmost importance for the safe and stable operation of the substation.

Upon learning about the background of the project, CHINT Mexico immediately organized transformer engineers to conduct on-site inspections and establish a special team. After multiple rounds of consultations and discussions, CHINT prioritized customer interests and project timeline, and ultimately proposed a solution that involved both component repair and complete replacement of the transformer.

Under this plan, CHINT would first provide components for repair to restore the transformer’s power supply, saving power generation and reducing losses. Meanwhile, CHINT would also supply a brand new 400kV replacement transformer with a delivery period of 120 days, ensuring the long-term stable power generation needs of the customer.

the-Heart-of-Mexican-Wind -Farm-20230313-1
the-Heart-of-Mexican-Wind -Farm-20230313-1
the Heart of Mexican Wind Farm 20230313 1

Within 120 days, from design to production; within 56 days, the new transformer was transported from Shanghai to Mexico; and within more than 30 days, the replacement installation and commissioning were successfully completed. All of these achievements are a result of the tireless efforts and contributions of every CHINT employee.

CHINT has always insisted on “customer-centric” principles, continuously improving delivery standards, and winning high praise through action. With CHINT’s “acceleration,” we have made a new contribution to the Mexican power market.

the-Heart-of-Mexican-Wind-Farm-20230313-2
the-Heart-of-Mexican-Wind-Farm-20230313-2
the Heart of Mexican Wind Farm 20230313 2
The Latest
DECEMBER 3, 2024 CHINT Supports China Unicom Data Center in Wuzhen ①

As a global leading smart energy solutions provider, CHINT leverages its integrated high-medium-low voltage solution to ensure stable power for the Wuzhen Intelligent Computing Center.

DECEMBER 3, 2024 CHINT Global Shines on Forbes Global Brand Top 30

The "2024 Forbes China Go-International Brands Top 30" results have been officially announced. CHINT Global has earned a spot on the prestigious list and is recognized for its outstanding performance and significant contributions on the global stage.

DECEMBER 3, 2024 CHINT and Qinghai Lihao Partner for Silicon Production

CHINT has partnered with Qinghai Lihao to build the world’s largest single-line production base for high-purity silicon in Xining, Qinghai Province.

DECEMBER 3, 2024 CHINT Attended the 2nd China International Supply Chain Expo

CHINT brought the whole industrial chain solution of electric power and new energy to the 2nd China International Supply Chain Expo.

DECEMBER 2, 2024 CHINT's Strategic Partnership in Renewable Energy Infrastructure

In the context of the global transition to renewable energy, CHINT has partnered with Tongwei Co., Ltd., a global leader in the high-purity polysilicon industry, to support large-scale energy projects.

DECEMBER 2, 2024 CHINT Industry Solution – Industrial OEM

Unveiling CHINT’s Industrial OEM solutions in our #IndustrySolutionSeries!

NOVEMBER 25, 2024 CHINT First Three Quarters Report of 2024

On the evening of October 30, 2024, we released the report of the first three quarters of 2024.

NOVEMBER 19, 2024 The Consulate General of Brazil in Shanghai & APEX Visited CHINT

The joint delegation of the Consulate General of Brazil in Shanghai and APEX visited CHINT for further cooperation and investment in Brazil and CHINT.

NOVEMBER 12, 2024 Interview with Ms. Lily Zhang, President of CHINT Global

Check out this exclusive interview with Ms. Lily Zhang, President of CHINT Global.

NOVEMBER 5, 2024 CHINT and Shanghai Baoye Reached Strategic Cooperation

CHINT Global and Shanghai Baoye signed a strategic cooperation agreement, and started a dialogue around the fields of electric power, new energy, housing construction and industry in the global region, exchanged cooperation opportunities in-depth, and explored a new prospect of sea business.