Please enter keywords to search

Global |EN

Choose your country & Language

Asia Pacific

Australia & New Zealand
India
Indonesia
Malaysia
Philippines
Singapore

Middle East & Africa

Kenya
Saudi Arabia
South Africa
United Arab Emirates

Europe

France
Kazakhstan
Netherlands
Spain
Italy
Turkey
United Kingdom

Latin America

Brazil
Colombia
Ecuador
Peru

North America

Canada
Mexico
United States

Choose your country & Language

Australia & New Zealand
India
Indonesia
Malaysia
Philippines
Singapore
Kenya
Saudi Arabia
South Africa
United Arab Emirates
France
Kazakhstan
Netherlands
Spain
Italy
Turkey
United Kingdom
Brazil
Colombia
Ecuador
Peru
Canada
Mexico
United States

Please enter keywords to search

Your search term contains restricted words. Please use different keywords.

CHINT’s Solar Milestone in Ecuador: Overcoming Adversity to Shine

AUG 12, 2023

CHINT-Solar-Milestone-in-Ecuador-4
CHINT-Solar-Milestone-in-Ecuador-4
CHINT-Solar-Milestone-in-Ecuador-4

On August 1st, the 9.65 MW rooftop distributed photovoltaic project for a renowned business group in Ecuador, undertaken by CHINT, was fully powered and connected to the grid in the city of Guayaquil. It passed inspections smoothly.

This project spans approximately 50,000 square meters of rooftop space, with an estimated annual power generation of 12.266 million kW·h, saving the client $1.2 million in electricity costs annually.

CHINT-Solar-Milestone-in-Ecuador-2.
CHINT-Solar-Milestone-in-Ecuador-2.
CHINT-Solar-Milestone-in-Ecuador-2.

After eight months of sales negotiations, CHINT finally secured the order. However, the journey was far from easy. The team faced numerous challenges including the global pandemic, local earthquakes, product losses due to client oversights and the need for restocking, structural reinforcements for many rooftops, and dispersed construction sites making project management difficult.

Nonetheless, with close collaboration between teams, the installation was completed in 1 year and 2 months without any additional costs, and the project was delivered on time and in full quality, earning high praise and recognition from the client.

At the project site located within the business intelligence park, rows of deep blue photovoltaic panels are visible. The project has a planned installation capacity of 9.6 MW, utilizing 450W bifacial mono-crystalline silicon modules and 60kW inverters.

It connects to the grid through low-voltage lines, achieving local power generation, grid connection, conversion, and usage. This approach effectively enhances the power output of photovoltaic stations of a similar size, addressing energy losses during voltage boosting and long-distance transportation

MW-rooftop-distributed-photovoltaic-project-1
MW-rooftop-distributed-photovoltaic-project-1
MW-rooftop-distributed-photovoltaic-project-1

In fact, as early as 2021, CHINT had already partnered with this Ecuadorian business group on a 7.75 MW photovoltaic project covering seven integrated rooftop facilities. Due to CHINT’s strengths, such as a specialized local team, comprehensive industrial chain, effective solutions, product quality, top-notch power station maintenance, and efficient technical support services, the client chose CHINT once again, deepening their collaboration on solar projects.

For this project, the client was driven by green, energy-saving, and eco-friendly principles. Supermarket rooftops with solar photovoltaic panels, rainwater siphoning systems, and glass curtain walls were all designed to maximize natural resource utilization and minimize energy consumption.

Hence, this project demanded high standards not just for power generation and grid connection, but also expertise and experience in electrical equipment installation and calibration.

MW-rooftop-distributed-photovoltaic-project-2
MW-rooftop-distributed-photovoltaic-project-2
MW-rooftop-distributed-photovoltaic-project-2

To meet these requirements, CHINT specially established a localized team in Ecuador comprising sales, electrical technology, project management, and civil construction management professionals. This laid a solid foundation for their future ventures in the region.

The CHINT Ecuador team possesses extensive experience in the installation of photovoltaic station electrical equipment and infrastructure construction. These strengths were fully showcased during the project execution.

From product quality control to installation standards, the team maintained stringent criteria, ensuring the system was not only aesthetically pleasing but also possessed high strength, rigidity, and reliability. Ultimately, thanks to the team’s dedication and collaboration, CHINT flawlessly delivered another “turnkey” project to the client.”

The Latest
APRIL 13, 2026 CHINT Showcased Its Largest Presence at FEICON 2026 and Announces Local Assembly of Air Circuit Breaker in Brazil

CHINT showcased its largest FEICON 2026 presence in Brazil, unveiling new power solutions and announcing local Air Circuit Breaker assembly for faster supply.

MARCH 31, 2026 Off-Grid Solar Street Lighting — Soran–Khlefan Tunnel and Mountain Road Safety Upgrade

Discover how an off-grid solar street lighting project in the Soran–Khlefan tunnel and mountain roads of Iraq improved visibility, road safety, and mobility with more than 20 solar-powered lighting poles built for remote, harsh environments.

MARCH 30, 2026 Powering the Future of Rotterdam’s EV Hub

NOARK ACBs ensure safe, reliable low-voltage protection for Rotterdam’s heavy-duty EV charging hub, delivering stable performance in harsh port environments.

MARCH 26, 2026 Enhanced CHINT Customer Service Network: Available Now in Asia-Pacific Region

CHINT launches upgraded Asia-Pacific customer service network with end-to-end support, multilingual access, and expert technical service for efficient global operations.

MARCH 24, 2026 Be Yourself, Everyone is Boundless! A Look Back at International Women's Day from Headquarters

CHINT celebrated International Women’s Day with flowers, blind boxes, and heartfelt activities, reflecting its commitment to DEI and women’s empowerment globally.

MARCH 2, 2026 CHINT Successfully Delivers First EMS Project in Vietnam, Enabling Smart Energy Management at NTCT

CHINT delivers its first EMS project in Vietnam, upgrading NTCT with smart low-voltage distribution and digital energy management for scalable campus efficiency.

MARCH 2, 2026 Embedding Sustainability into Long-Term Growth: CHINT Group’s Key ESG Achievements of 2025

CHINT Group advances its 2030 ESG strategy in 2025 with SBTi targets, green supply chain innovation, top ESG ratings, and scalable zero-carbon solutions.

MARCH 2, 2026 CHINT Group 2026 New Year Conference : Green & Intelligent Synergy

CHINT’s 2026 New Year Conference highlights Green & Intelligent Synergy, AI First strategy, and 185B RMB revenue, driving global growth and innovation.

JANUARY 30, 2026 CHINT Secures SBTi Validation, Anchoring Global Climate Action in Science

CHINT earns SBTi validation, joining 10,000+ firms with science-based climate targets and advancing zero-carbon factories, green products, and PV+ solutions.

JANUARY 30, 2026 A Deep Dive into CHINT Green Energy Solutions White Paper 2025

Explore CHINT’s Green Energy Solutions White Paper 2025, highlighting decarbonization pathways, smart grids, energy storage, and zero-carbon solutions.