Introduction
Overview
CHINT delivered a complete high-voltage electrical solution for the 13.86MWp solar plant in Serbia, including 35kV substations and transformers. The project was completed in just 3 months, supporting Serbia’s green energy transition with an annual output of 10.62 million kWh.
Scope of Supply
35kV pre-fabricated substation, 35kv dry-type power transformer, 35kv high-voltage switchgear, 35kV oil-immersed power transformer.
Solutions
Complete solution for electrical equipment on the high-voltage side of the 35kV PV power plant.
Challenges
-Short delivery period: From contract signing in July 2023 to shipment in October 2023, it just took 3 months.
-CE certification meeting local special requirements.